TrainRiders/NE Endorses NNEPRA's Proposed Portland Station Move to the Mainline, but with Important Concerns
- Details
- Created: 28 August 2024 28 August 2024
The NNEPRA proposal to move the Portland Station from the Transportation Center to the mainline has received multiple public comments. Saving running time for passengers, crew, and equipment and significant annual cost savings (estimated at nearly $1 million) are accepted reasons to update the awkward move back and forth on the Mountain Division spur.
TRNE President F. Bruce Sleeper has entered public comments on behalf of our board, members, and train riders in general. In summary:
TRNE "heartily supports" the selection of site 3. "It presents the fewest operational difficulties" and accomplishes the NNEPRA goals of reducing the running time between Brunswick and Boston as well as significant cost savings.
TRNE has concerns about certain elements of the Site 3 proposal.
- The proposed station's passenger capacity appears "far too small" to handle the growing Downeaster ridership trend. Amtrak's guidance for station size calls for significantly greater square footage for waiting passengers.
- The parking area, which would accommodate105 vehicles, is too small. "The station should include at least 200 parking spots and probably even more, preferably on-site." In addition, the parking area's configuration could leave some passengers some 500 feet from the station...not an attractive condition during the winter.
These concerns are buttressed by statistics, experience at Amtrak and Downeaster stations, as well as Amtrak guidance.
Mr. Sleeper's comments to NNEPRA concludes, "TRNE appreciates all of the work that has, thus far, gone into this project and hopes that its comments are helpful and will be given the consideration that they deserve. TRNE understands that the only issue now at hand is whether Site 3 is the appropriate location for the new station. As stated above, TRNE firmly supports that site for the new station, and it makes its additional comments only to ensure that the issues those comments address become part of the ongoing process for the construction of that station. Full TRNE comments to NNEPRA
TrainRiders/Northeast - Changing the Way New England Travels.
Renew, join or provide special financial support by going here!
NNEPRA Settles on Site for New Portland Station
- Details
- Created: 22 August 2024 22 August 2024
This article provides additional details on NNEPRA's decision to move its Portland Station from the Transportation Center to the mainline. Three possible relocation sites were analyzed, and NNEPRA decided on a St. John Street location opposite the Metro bus headquarters.
https://www.nnepra.com/project/portland-station-relocation/
The new location would shave 15 minutes off Amtrak Downeaster's northbound and southbound trips - time now spent moving the train on and off a branch of the CSX main line to reach the existing station at the Portland Transportation Center at Thompson's Point.
According to NNEPRA, the move would eliminate 20 train movements daily along the spur and would save nearly $1 million in labor and fuel costs annually, while also improving access to and reliability of the Downeaster.
It's unclear how many private properties along St. John Street would have to be purchased or taken by eminent domain.
NNEPRA is seeking public comment on the chosen location and conceptual plan through Aug. 27.
The future site, chosen in June by the authority's board of directors, is located just south of the spur, which would allow the train to remain on the mainline when traveling between Brunswick and Boston.
Selected from three possible sites along St. John Street, it also meets the authority's goals to improve access to vehicle, pedestrian and bicycle connections, public transit, train maintenance and additional rail service, according to the proposal.
"This site provides the most opportunity and flexibility for train operations," Patricia Quinn, executive director of the authority, said in a phone interview Monday. "It also really maximizes connectivity for rail access and mobility."
Two other sites considered were further north along St. John Street, on either side of Congress Street. One was adjacent to the Cumberland County Jail and a strip mall that replaced the Union Station complex, which was torn down in 1961. The other site was on the west side of the main line tracks, behind McDonald's, Amato's and other businesses between Congress Street and Park Avenue.
MaineHealth had a variety of safety concerns about the potential impact of moving the station near the strip mall, according to the proposal. Northern Light Mercy said it would "work collaboratively to explore options" for the preferred site "that can be mutually beneficial as long as the integrity of our campus and the safety of our employees and patients are preserved."
The proposal for a new station, including an architect's conceptual rendering and a form to submit feedback, is posted on the authority's website.
Next steps in the planning process include developing preliminary engineering and environmental compliance plans and a cost estimate for the project; and seeking federal funding and non-federal matching funds for final design and construction.
Quinn has said previously that a new train station and platforms would cost $25 million to $30 million and could be completed within five years.
How many or which properties along St. John Street would have to be purchased or taken by eminent domain is unknown, Quinn said. The project area hasn't been surveyed, but property owners who would be affected have been notified, she said.
"We're very early in the process," she said. "We haven't begun negotiations."
Also unknown is whether the preferred site would satisfy the authority's goal to provide 105 parking spaces at the new station, Quinn said.
According to the proposal, the new station would include adjacent parking with a circulation area for passenger drop off and pick up.
It also would include two boarding platforms — one on each side of the main line tracks — within the railroad right of way; a federally compliant accessible pedestrian bridge over the tracks; and a 750-square-foot, climate-controlled passenger waiting area with ticketing and restrooms.
"A main line station with double platforms would only require a two-minute station stop," the proposal states.
An article reported in Mass Transit Magazine - originally pubished in the Portland Press Herald
TrainRiders/Northeast - Changing the Way New England Travels.
Renew, join or provide special financial support by going here!
Amtrak Downeaster Sets All-time Ridership Record!!!
- Details
- Created: 07 August 2024 07 August 2024
'America's Favorite Train' set an all-time record in FY 2023-2024 by transporting nearly 600,000 passengers between Brunswick and Boston. With five round trips daily, a total of 598,426 riders left their cars behind, relaxing to and from their ME, NH & MA destinations. NNEPRA notes that the previous record of 575,000 was set 2019.
We had a conversation with Natalie Bogart, NNEPRA Deputy Director, about the amazing ridership and revenue achievements.
Ten of the 12 months in the just completed fiscal year set new records!
A full article from the Portland Press Herald article can be viewed here.